Total Advising Construction is Making Clemons Library Better than Before!

Since January of 2016 the 2nd floor of Clemons Library has been a construction site. Students and staff on the 3rd and 1st floors have endured the inevitable noise. The payoff is that the Dathel and John Georges Student Center … Continue reading

Planned Power Outage in Clemons Library, June 7–9

A power outage is planned in Clemons Library that will begin at 6:00 a.m. on June 7 and last through 3:30 p.m. on June 9. The outage is necessary to allow work to proceed on Clemons’ Total Advising center on … Continue reading

Facilities Management Modifies Clemons Construction to Meet Students’ Concerns

In response to student concerns about the noise from construction on the roof and second floor of Clemons Library at a time when quiet study space is needed to prepare for upcoming exams, Facilities Management has agreed to modify work … Continue reading

Total Advising Student Workshops

Want to have a positive impact on student life at the University? The Provost’s Office is holding workshops for students and other stakeholders to share thoughts and suggestions about Total Advising at UVA. Workshops will be held on Tuesday, February … Continue reading

Total Advising Update

Construction on the Total Advising Center planned for Clemons Library has been postponed in order to avoid disruption to students during the spring semester. The Office of the Provost will continue to solicit student input on the project. Questions about … Continue reading

Total Advising Coming to Clemons Library

Beginning in January 2017, Total Advising, part of President Sullivan’s Cornerstone Plan, will transform the second floor of Clemons Library into a centrally-located resource where students can get information about academic and career options. Whether they need counseling on careers, … Continue reading